NHPC blames BHEL for supply delays

NHPC Limited's 45 MW Nimoo Bazgo hydroelectric project unlikely to go on steam by its latest expected commissioning date of October 2011.

 

The state-run utility has requested the contractor, Bharat Heavy Electricals Limited, to supply electro-magnetic equipment without any further delays, as the road access, that was shut since December last year, has now been opened.

Besides, the river diversion, programmed for April 2011, is now expected by October 2011.

Further, powerhouse concreting, critical for the completion of the project, is anticipated to be concluded by August this year. As of May 18, 2011, 17,636 cum of concrete, out of the total 23,000, has been laid out.

As far as dam concreting is concerned, as against the target of 1,84,695 cum, 1,49,341 cum of concrete has already been laid out, and the remaining 5,364 cum is expected to be completed by December this year.

The Board of NHPC has given its approval for the project's plan outlay of Rs138.60 crore for the financial year 2011-12. The sanctioned amount is almost 40% less than the outlay of Rs 232.68 crore, approved for the previous financial year.

The project is a run-of-river scheme, planned to harness the hydropower potential of the Indus river, in the Leh district of the state. The project would afford an annual energy generation of 239 million units, assuming 90% performance.


 

Follow the link for more news on

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.