Myanmar dam failure floods 85 villages

Authorities had given an all-clear to the dam despite overspill concerns.

Reuters reports that as many as 85 villages were flooded in Myanmar after a dam failure unleashed waters that blocked a major highway and forced over 63,000 people to evacuate from their homes, a state newspaper said.

A rescue effort was launched after the spillway of an irrigation dam burst at Swar creek in central Myanmar, sending a torrent of water through villages and the nearby towns of Swar and Yedashe. Two people remained missing and were feared to have been washed away, said Min Thu, deputy administrator of Yedashe.

Traffic between Myanmar’s major cities of Yangon and Mandalay and the capital, Naypyitaw, was disrupted after the flooding damaged a bridge on the highway linking the cities.

A priority was to get as much water into the reservoir as possible before the dry season when it is needed for irrigation, said Kaung Myat Thein, an irrigation official at the Ministry of Agriculture, Livestock and Irrigation. He said a probe would seek the cause of the dam breach.

“The retaining wall of the spillway sank into the foundation about 4-5 feet, causing the flooding, but the main dam is intact,” said the official.

Days before the breach, authorities had given the all-clear to the dam, which can hold 216,350 acre-feet of water, despite residents’ concerns about overspill, state-run media have said. This highlights safety concerns about dams in Southeast Asia after a collapsed hydroelectric dam in Laos displaced thousands and killed at least 27 people.

Read the full report here.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.