NHPC's Uri-II hydro project on track for December commissioning

NHPC has completed dam excavation and concreting for its 240 MW Uri-II hydroelectric project in June with all four unit on track for commissioning by December 2011.

 

Each unit has a capacity of 60 MW. 

The Uri HEP has also made significant progress in overt and invert lining associated with head-race-tunel works. The lining is nearing completion for junction points and D/s Adit-III. In addition to this, TRT excavation and power house concreting was completed during the month.

Trial run of spillway radial gates 1, 2 and 3 was successfully conducted, following which erection of SRG 4 has begun. Erection of trash rack of head regulator gates and HRT intake gates has concluded whereas boxing up of unit 3 is progressing sequentially. Furthermore, the coffer dam was restored and work on critical activities such as radial gates and civil works was restarted in beginning of June.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.