Vietnam rolls out more stringent rules for wind power projects

Additional feasibility requirements will be implemented.

Vietnam’s Ministry of Industry and Trade (MOIT) has unveiled updated guidelines for the development of wind power projects in the country. Under Circular No. 02, the MOIT addressed several areas which previous regulations have failed to cover, such as documentary requirements, feasibility studies, safety regulations, and others.

The Circular provides a comprehensive list of documents required for the approval of a newly proposed wind farm, such as an assessment report of wind potential, preliminary project design, written consent and opinions from the provincial People’s Committee, and written opinions from the EVN.

It also requires wind power projects to have a report on wind measurement data at the proposed site before a feasibility study (FS) report is formulated and approved. Unlike previous regulatons, Circular No. 02 provides greater flexibility by stating that the method, equipment and results of wind measurement tests must conform to international standards of the International Electrotechnical Commission (IEC) or an equivalent international standard.

The Circular also provides for the process of testing and commissioning wind farms, as well as requirements for turbines and equipment. The new rules also provide a reduced maximum land use area for wind farms. For instance, a wind farm may not exceed more than 0.35 ha per MW for permanent projects, compared to 0.5 ha per MW previously. For temporary projects, the rate of land area may not exceed 0.3 ha per MW, instead of 0.7 ha per MW under previous rules.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.