Vietnam may face 6.6 billion kWh electricity shortage in 2021

47 out of 62 power projects are delayed.

Vietnam could face an electricity shortage of 6.6 billion kWh in 2021 and 11.8 billion kWh in 2022, a report by Vietnam Plus revealed.

The shortage is blamed on the delayed progress in 47 of 62 power projects, with capacities of more than 200MW, under Vietnam’s Power Master Plan VII, explained Electricity and Renewable Energy Authority’s director Phuong Hoang Kim.

Also read: Winds of change: Vietnam pushes for more developments amidst growing energy demand

The main reason for the delayed progress was blamed on capital and contractor issues, as well as the removal of the government guarantee mechanism for power projects, which has made it difficult to raise capital.

VIetnam has implemented power projects in three investment models including those invested by Vietnam Electricity (EVN), the Vietnam National Oil and Gas Group (PetroVietnam) and Vietnam National Coal and Minerals Group (Vinacomin), as well as build-operate-transfer (BOT) projects and independent power producer (IPP) projects.

“It took a long time for BOT projects to negotiate power prices with EVN to ensure their profits, thus causing delays,” the report noted, adding that prolonged land clearance and low power tariffs have not made the situation easier.

Deputy minister of industry and trade Hoang Quoc Vuong proposed that the government should promote the implementation of renewable energy projects as they take a short time to complete. According to EVN, it only took six months for them to implement a solar power project whilst that of a 220kV or 500kV plant took three to five years.

“He added that the ministry would consider importing electricity from Laos and China to resolve the power shortage. However, this would be a temporary solution. The country should accelerate the progress of large power projects,” the report said.

Also read: IPPs push projects into Vietnam's open electricity market

In H1 2019, electricity consumption jumped 10% YoY because of the prolonged hot weather, and power consumption is expected to increase by another 10% by end-2019.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.