3GW of India's solar and wind installations face delays

The country’s solar industry relies heavily on Chinese PV module imports.

Over 21.6% or 3GW of solar and wind installations in India could be delayed as a result of the country’s lockdown, according to a report by Wood Mackenzie.

Solar installations are set to be hit hard by the lockdown as the industry is heavily dependent on Chinese photovoltaic (PV) module imports, which account for 80% of the total volume.

According to Wood Mackenzie senior analyst Rishab Shrestha, solar installations are projected to crash 60% YoY in Q1, or 1.2GW out of 3GW during the quarter.

The report is bearish about PV installations in the second half of the year, as supply and logistics bottlenecks linger. Shrestha projects solar installations to fall 24.8% to 8.9 GW in 2020.

Meanwhile, principal analyst Robert Liew explained that wind project installations tend to rise in Q1. If the lockdown were to be extended past April, wind farm construction could be further delayed into the monsoon season, where wind installations are typically at their lowest.

With over 3GW of wind projects under construction scheduled for 2020 completion, supply and labour disruptions from the lockdown could delay 400MW into 2021, causing installations to fall 11% for 2020.

Further, states with the highest infection rates happen to be areas that are favourable to wind and solar development. For instance, Gujarat delivered 58% or 1.4GW of new added wind capacity in the country in 2019, but stands as one of the worst hit states in terms of coronavirus infections.

In terms of solar installations, Karnataka (2GW), Tamil Nadu (1.6GW) and Rajasthan (1.7GW) accounted for 55% of the country’s total in 2019, whilst also being amongst the worst hit states. 

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.