Powergrid defers construction of bays for 2 projects

The Talcher-II and North Karanpura transmission projects habe been deferred due to the ambiguity in the commissioning schedules.

 

Both companies awarded with the projects--Reliance Power Transmission`s arms - North Karanpura Transmission Company Limited and Talcher-II Transmission Company Limited--have sought the shifting of the zero dates and an extension of the overall commissioning schedule for these two transmission projects, along with higher tariffs.

In light of the uncertainty in commissioning schedules of the proposed schemes, the Central Electricity Authority has been forced to direct Power Grid Corporation of India Limited to defer the construction of bays and reactors associated with these projects, until a concrete decision is taken on the matter.

The power evacuation for the Talcher-II project, which is aimed at providing back-up in case of outage of the Talcher-Kolar HVDC link, is likely to be severely impacted as a result of this move. The Talcher-Kolar bipole line was initially built to evacuate power from the 2,000 MW Talcher-II super thermal power station to its southern region beneficiaries.

Concerned with the ambiguity regarding commissioning of the North Karanpura transmission project, Central Electric Authority has claimed that PGCIL will face tough times ahead for evacuation of power from this proposed scheme. The unresolved issue has already hampered the development of the project to a large extent.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.