Early bidding necessary for Tanjung Bin Plant: Energy Commission

Malaysia's Energy Commission clarified that the bidding process for the Tanjung Bin Power Station project was conducted five years before it begins operations in 2016 because of the lengthy construction period.


It explained that construction of such a large-scale power plant will require at least five years on a brownfield site.
The project in Johor, which is to develop and operate the 1,000 MW coal-fired power plant, was awarded to Transpool Sdn Bhd, a subsidiary of Malakoff Corporation Bhd, via a competitive restricted bidding process conducted by the Commission from Nov 15, 2010 to April 15, 2011.

The project is needed to meet the projected demand in 2016 following the cancellation of the proposed submarine cable from th Bakun Hydroelectric Project.

"Greenfield development will require a longer period to undertake the Full Environmental Impact Assessment, detailed site identification and assessment, including public consultation, site preparation, reclamation and soil investigation and construction of new transmission and interconnection facilities, coal handling and other common facilities.

"Based on the projected economic growth, failure to award such a project on time to achieve commercial operation in early 2016 will result in potential brownouts in the country," the commission said in a statement today.
It was responding to a recent statement by Petaling Jaya Utara MP Tony Pua.

The Energy Commission said the brownfield site option was chosen for the bidding process.

The full story is available at Bernama News.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.