NHPC advances Rs 10 crore to mitigate contractor's cash crunch

NHPC has now approved an interest bearing advance of Rs 10 crore against a secured bank guarantee to Hindustan Construction Company, contractor of its Uri-II hydroelectric project. Thge latter is experiencing a cash flow crunch.



Further, NHPC`s board of directors are in the process of considering an additional interest bearing advance of Rs 15 crore to HCC.

The project has not seen any progress towards completion of the head race tunnel (HRT) lining, a milestone critical for the 240 MW HEP, in the month of October, contrary to its progress in September. The balance works stand at the same level as the previous month, with 32 m of overt lining and 40 m of inert lining yet to be finished.

The works associated with tail race tunnel lining have been expedited. The progress of inert lining fell short of its target by 24%, with 435 m out of 573 m achieved during
the month.

The project cost is now being anticipated at a total cost of Rs 1,794 crore, 5% higher than earlier level of Rs 1,706 crore. The cumulative expenditure on the project stands at Rs 1,575.98 crore, up to October 2011.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.