, India

Power ministry on UMPPs-II: Projects set for completion ahead of schedule; dates for all five units of Mundra UMPP pushed forward

From the commissioning schedule of ultra mega power projects (UMPPs) provided by the power ministry, it seems that the the projects are well on track with respect to their completion timelines. For instance, CEA has revised the timelines for all five units of the 4,000 MW Mundra UMPP so that the projects may achieve commissioning much earlier than was originally envisaged in the PPA schedule.


For the 800 MW unit 1, CEA has pushed the commissioning date forward by nearly five months to February, 2012 as against the scheduled commissioning date of August, 2012.

The CEA has similarly revised the commissioning dates for the remaining four units. The new dates for the four units are now May, 2012 (unit-II), September, 2012 (unit-III), November, 2012 (unit-IV), and February, 2013 (unit-V) as against the original schedule where the the units were expected to go on steam form February, 2013, August, 2013, February, 2014 and August, 2013 respectively.

The Mundra UMPP has been set up by Coastal Gujarat Power Limited (CGPL), a wholly owned subsidiary of TPIL, which was incorporated as a Special Purpose Vehicle (SPV) to implement the project. The five units of 800 MW each generate a total of 4000 MW power using supercritical technology.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.