, India

NHPC project gets delayed again due to BHEL's sluggishness

The chances of NHPC commissioning the Nimoo Bazgo hydroelectric project on the revised schedule appeared increasingly bleak after BHEL delayed milestones.

 

The power house concreting, which has been delayed repeatedly over the past few months, has witnessed no progress during the previous month.

Currently, 3,208 cum of concreting, out of the cumulative 23,000 cum, remains to be concluded. In contrast to this, the dam works have advanced much more than the projected target for the month of December 2011.
 
Although 500 cum was scheduled to be laid out for left side non overflow blocks for the month of December, Bharat Heavy Electricals Limited has managed to achieve 600 cum, thereby bringing the cumulative work concluded up to 12,485 cum, out of the total of 42,800 cum.

To note, the 45 MW project is a run-of-river scheme, planned to harness the hydropower potential of the Indus river, in the Leh district of the state. It envisages the construction of a 57 m high concrete gravity dam, three 6.3 m long penstocks, with a diameter of 3.3 m, each, and a surface power house with four Francis turbine units of 15 MW capacity, each. The project would afford an annual energy generation of 239 million units, assuming 90% performance.

Follow the link for more news on

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.