, India

Italian-Thai Devt eyes criticality for Indian dam by Oct 2012

Italian-Thai Development has committed to achieve dam readiness for NTPC's 800 MW Koldam hydroelectric project and commencement of reservoir impounding by October 20.

 

The Koldam HEP is located in district of Bilaspur, at an approximate distance of 25 km from district HQ on river Satluj and 4 km upstream of Dehar power plant.

The civil works contractor encountered a slew of geological constraints at the project site.

A slide on the right bank, compounded by seepage problems in the main dam clay core area, has increased the amount of work required to be put in by ITD on spillway concreting and gallery grouting. In addition to this, a right bank slope failure, along with the subsequent rectification works, has caused further delays at the dam.

With ITD putting in its best efforts to conclude dam activities at the earliest, it is likely that the water, crucial for commissioning of all four units of the power project, will be available by the end of FY 2012-13.

But while the works at the project level are progressing swiftly, those at the inter-ministerial level remain stuck. No concrete decision has been made by the Ministry of Environment and Forests on NTPC's request for withdrawal of mitigation charges or up to 5% of project cost.

The National Board for Wildlife has yet to accord clearance of the Majathal wild life sanctuary area, that comes under the submergence of Kol Dam.

The estimated annual generation of electricity is 3,054 GWh in a 90% dependable year.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.