Nam Ngiep 2 dam takes shape ahead of schedule

Construction of the Nam Ngiep 2 hydropower plant in Xieng Khuang province is about 10

percent complete, after the project officially got under way in December.

The work is going faster than the scheduled progress by about 2 percent, according to a

press release issued following an inspection on Sunday by Xieng Khuang provincial Governor

Prof. Dr Somkot Mongnomek and two Energy and Mines Deputy Ministers, Mr Viraphonh Viravong

and Mr Khammany Inthirath.

Prof. Dr Somkot Mongnomek ( fifth left ), Mr Khammany Inthirath ( second right ) and Mr

Viraphonh Viravong (behind) compare the construction site with the project plan.
The Governor highly praised the progress and quality of the construction, the press release

noted.

Construction of the hydropower plant began last October and the project is scheduled for

completion at the end of 2015.

So far, about 95 percent of te mporary facilities have been completed, including working

faces for the main dam, a diversion tunnel, a headrace tunnel, a tributary tunnel, a

tributary dam and power house, the press release noted.

The dam is located in Phaxay and Khoun districts, about 30km southeast of Xieng Khuang

provincial capital. It is being developed by the Nam Ngiep 2 Power Company Limited, which

is a joint venture between China International Water & Electric Corporation (CWE) and

Electricite du Laos (EDL).

CWE President Mr Wang Yu said at the groundbreaking ceremony that the project involves a

total investment of 2.7 trillion kip (US$345 million). CWE holds a 90 percent share in the

company and EDL holds a 10 percent stake.

The dam will have an installed capacity of 180MW and will generate 723 million kWh per

year. EDL will buy all the electricity generated to feed into the national power grid.

EDL Managing Director Mr Sisavath Thiravong said the plant is expected to earn revenue of

about 348 billion kip (US$43.38 million) per year.

The Nam Ngiep 2 project will mainly supply provinces in the north-east, as this region

still does not have enough electricity to meet local demand.

Xieng Khuang provincial Deputy Governor Mr Khampiene Sinuanethong said recently that only

62 percent of all households in the province have access to electricity.

In addition to electricity, the power plant will provide benefits in the areas of flood

control, irrigation, transportation and tourism, which will promote local social and

economic development.

The developers signed a project concession agreement with the Lao government last August.

The concession period is 25 years, starting from the date of commercial operation.

CWE entered the Lao hydropower market in 1996. They have since invested in the Nam Leuk,

Nam Mang 3 and Nam Lik 1-2 dams. They have also invested in the installation of power

transmission lines and substations.
 

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.