Siemens to supply turbines to Australian combined cycle power station

Siemens Energy will supply €150 million worth of turbines for the proposed 242MW Diamantina combined cycle power plant in Mount Isa in Queensland, Australia.

 

The turbines are two power islands each comprising one SST-400 steam turbine, two SGT-800 gas turbines and two heat-recovery steam generators.

The installed capacity of the plant will be sufficient to supply electricity to local mines operated by Xstrata and to people living in the region.

The first block of the Diamantina power plant is scheduled to commence full commercial operations in late 2013 and the second block will start up in early 2014.

Siemens Energy's industrial power business unit CEO Markus Tacke said the power station is a great example of ecofriendly power supply solutions for different industries worldwide.

The company will also be responsible for the overall plant design and will provide technical advisory services during theconstruction and commissioning phases of the project.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.