BHEL's lackadaisical attitude a cause of serious concern for NTPC's Rihand STPP

In yet another disappointing turn of events for NTPC`s Rihand super thermal power plant (STPP), power equipment major BHEL has failed

to fast-track the supply of the critical steam generator (SG) package for unit 6 of the project.
8The resources, which include the equipment for ducting, fan and oil systems, have not been delivered to the project site till now, leading

the power utility to persuade BHEL to take concrete action on this front on priority basis.
8To add to its woes, the project developer has already been struggling to convince National Buildings Construction Corporation Limited (NBCC)

to hasten the pace of works associated with the cooling towers (CT) which have been thrown off-track completely in the past few months due to

the contactor`s failure to augment necessary resources.
8Therefore, it is pertinent that the contractors - BHEL and NBCC - take immediate remedial measures in order to avoid any further slippages in

the commissioning of the project.
8To note, the project was conceived as a coal based super thermal power plant of 2,000 MW capacity. It is located on the southern bank of

Rihand reservoir near village Bijpur in District Sonebhadra of Uttar Pradesh and it touches the boundary of three states MP, Chhattisgarh and

Jharkhand.
8A cumulative sum of Rs 2,644 crore has already been expended on the project till January 2012 since inception. The total expenditure incurred

during this fiscal, up to January this year, stands at Rs 950 crore against the total annual plan outlay of Rs 1,298 crore.
(Click on our `Reports` section for more information)

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.