, China

Laxiwa’s Unit 1 now connected to grid

All five Laxiwa Hydropower units are now connected to the grid after its Unit 1’s successful commissioning. The unit recently completed a 72-hour test run.

Widely acknowledged as an extremely challenging large hydropower project, Laxiwa Hydropower Station of Huanghe Hydropower Development Co., Ltd. features the highest dam, largest installed capacity, largest power generation and good economic index in the Yellow River Basin.

With construction preparations started in October 2001, the project had riverbed cutoff in January 2004, first dam concrete pouring in April 2006, water storage in March 2009, first two units connected to grid for power generation in May 2009 and the third at the end of September 2009. Laxiwa Hydropower Station has also created a series of records in hydropower construction of China – 7.5 years from construction preparation to water storage, 3 years from first dam concrete pouring to first unit generating electricity, 9 days for commissioning of first unit, and launch of 4×700MW units within one year.

The successful commissioning of Laxiwa Hydropower Station Unit 1 has laid a solid foundation for CPI Huanghe Hydropower Development Co., Ltd. to hit the goal of exceeding 10GW hydropower installed capacity in Qinghai province in 2010.

Follow the link for more news on

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.