, Philippines

Philippines' TeaM Energy shortlists contractors for coal-fired plant expansion

TeaM Energy now has six firms as prospective boiler supplier; and another six for the turbine  the 400-megawatt expansion of the Pagbilao coal-fired plant.

 

This was disclosed by company president and CEO Federico E. Puno.

TeaM Energy, the operator of the existing 735-MW Pagbilao facility, will be partnering with the Aboitiz group on the capacity expansion of the pulverized coal-fed power facility.

The shortlisted firms include Mitsubishi Heavy Industries which was also the original equipment manufacturer in the first two units of the Pagbilao facility. The others are Hyundai Heavy Industries, European firms Alstom and Foster Wheeler AG, American firm Black & Veatch and Japanese firm Toshiba Corporation.

Being the OEM for the first two units, Puno has indicated that they are open to negotiating with Mitsubishi on the expansion’s turnkey contract “if they will give us a good price.”

The technology deployment for the third Pagbilao unit will follow the first two because it will be a more cost effective way of implementing the project.

The capital outlay for the facility’s expansion has been placed at $600 million to $700 million.

Puno added that they are still finalizing the specifications of the proposed unit, including a prospective lower calorific value of coal that will be utilized in running the facility.

He stressed that the perceived advantage in the design of the third unit will be its ability to burn coal with lower calorific value of 4,200 k/cal as compared to 6,000 k/cal in the initial units.

The expanded capacity of the Pagbilao plant is targeted on-line by 2015, the period when supply shoring up will be needed again in Luzon. This will be after the 2013 commercial operation of the 600-megawatt plant of GN Power.

For more.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.