Delayed supply by BHEL hits NTPC's Rihand STPP-III hard

Delay in supply of steam and turbine generator components by BHEL is keeping the 500 MW unit-II of the Rihand stage-III expansion project in India from being comissioned on time.

Another issue that has created problems for the project is insufficient manpower for cooling tower works being executed by NBCC. Augmentation of manpower and timely delivery of equipment is a must, if NTPC is to commission the unit by March 2013.

The project is already running behind schedule. Earlier, the sixth unit of Rihand STPS was programmed to be commissioned by October 2012.

However, non-resolution of the above matters has forced NTPC to extend the timeline to end of FY 2012-13. If NTPC fails to convince the contractors to expedite respective works, the project will most likely slip into the forthcoming financial year.

BHEL had bagged NTPC`s contract in 2009 for the supply of the steam generator and electro static precipitator combined package to the 2X500 MW Rihand-III thermal power project being set up at the Sonebhadra district in Uttar Pradesh at a negotiated price of Rs 1,492 crore.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.