, Malaysia

Four turbines of Malaysia's Bakun hydel dam to be commissioned

Sarawak Hidro will commission the remaining four of the eight turbines at Bakun hydroelectric dam by stages in the second half.

The installation of the fifth to eighth turbines from Argentina was in progress and that they would be commissioned in stages, said managing director Zulkifle Othman.

“Testing of the fifth turbine is expected to be carried out in March next year,” he noted.

The commissioning will ramp up full-power generation capacity.

Each turbine has a generation capacity of 300MW.

Zulkifle said 1,200MW of electricity was available for use by state-owned Sarawak Energy Bhd following the recent commissioning of the fourth turbine from Alstom.

He said SEB's daily consumption of Bakun power fluctuated between 300MW and 750MW.

“Whatever demand (from SEB), we will give,” he added.

Bakun dam in the upper Rejang River basin in central Sarawak has an installed capacity of 2,400MW.

For more.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.