, India

IL&FS to set up 4,000 MW super-critical thermal power plant in Gujarat

Infrastructure financing and project development firm IL&FS (Infrastructure Leasing & Financial

Services Ltd) has requested the coal ministry to provide long term coal linkage for its upcoming 4,000 MW

coal-fired power plant in Gujarat. The project, scheduled to start in June, 2017, would be the single-largest

private generation power project in the country.
8IL&FS has floated a special purpose vehicle, Nana Layja Power Company Ltd (NLPC), for implementing the project

in the Mota Layja village of the state's Kutchh district.
8The project, which is part of the Special Economic Zone (SEZ) that IL&FS is setting up in Gujarat, will be set

up with super-critical technology and a desalination plant of 60 MLD capacity.
8The utility has proposed to use blended coal in the ratio of 70 (Indigenous) : 30 (Imported) as a feed stock

for the thermal plant.
8"NLPCL has already initiated for tie-up of 30% of total required coal from the mines of Australia/ Indonesia/

USA/ South Africa and 70% of the total required coal would be indigenous for which coal linkage application is

being submitted.", IL&FS said in a recent missive to the coal ministry.

L&FS has submitted to the coal ministry the current status of the various milestones associated with the

coal-based project.
8Land Acquisition: The project would require approximately 1,350 acres of land including the green belt. Most

of the land has been acquired by the SEZ Company and NLPCL has entered into an MoU with the SEZ Company for

transfer of the land on 45 years lease basis. Most of the land is fallow or barren land.
8Project Development Studies: The Detailed Project Report (DPR) for the TPP has been completed. The site

specific Flora and Fauna studies, Geotechnical studies, Hydrological studies and Topography survey of the site

have also been completed. Seismic Study, Comprehensive Socioeconomic Study, EIA study is underway.
8Power Off-take: It is proposed to tie-up 85% of generated power on long term basis with utilities through

Case-I bidding process and remaining 15% through short term tie up.
8Power Evacuation: The project would be connected through PGCIL transmission lines up to the nearest Regional/

National Grid system. Beyond the Regional/ National Grid system, Long Term Open Access would be sought from

PGCIL/ RLDC. Load flow studies will be done by PGCIL.
8Captive Port: It is proposed to unload the imported as well as domestic coal at Captive Jetty being set up by

the IL&FS Group Company at sea side which is around 8 km south from the TPP site. Application for GMB (Gujarat

Maritime Board) permission for above jetty has been submitted and approval is awaited.
8Supply and Erection Contracts: Supply and Erection orders for Main and BoP will be placed to suitable

suppliers and contractors upon achieving financial closure. The supply and erection orders are expected to be

finalized by August 2013.
8Environment Clearance: MoEF has prescribed the terms of reference (ToR) for carrying out the environment

impact assessment (EIA) dtudies during its 36th meeting held on 14-15th November 2011. EIA studies are

currently underway. It is expected to complete public hearing by April 2013 and final Environment Clearance

(EC) by June 2013.
8AAI Clearance: AAI has provided the No Objection Certificate (NOC) for construction of Chimney.
8Water Linkage Clearance: The project is based on sea water and GMB has granted permission for drawl of sea

water and also issued NOC for construction of sea water intake and outfall structures.
 

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.