Russian contractors blamed for delay in Indian thermal project

NTPC blamed two Russian suppliers for for the delay in its 1,980 MW Barh I super thermal power project.

Many critical milestones are pending due to the shoddy performance of Russian firms Power Machines and Technopromexport.

The two Russian contractors have failed to pick up pace and conclude balance works despite NTPC's repeated requests.

The contractors' non-adherence to the approved schedule has become so critical that the Power Ministry may intervene to help resolve NTPC's contractual woes.

One of the biggest worry for NTPC is Power Machines' delay in boxing up of the turbo generator set, oil flushing and commencement of condenser erection.

The Russian supplier was supposed to complete all the above stated milestones by December last year but the delay in works has postponed the target date by at least a year to January 2014.

On the other hand, TPE has not completed the supply arrangements of critical bought out items (BOI), including pulverised fuel pipes (PF pipes), equipment cooling water (ECW) system and support structures for air and gas ducts.

Moreover, TPE has delayed the procurement of the Indian Boiler Regulation (IBR) certificate necessary for erecting pressure-parts of a turbine. The contractor has, however, committed to complete the pending work by March 2013.
 

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.