Rift with Pakistan ups Indian power project costs

The water disputes between India and Pakistan are making the costs of hydroelectric projects escalate, say India’s power department officials.

The cost of the 330MW Kishenganga project has gone up from approximately $490 million to $800 million, according to statistics provided by the power development department. The deadline for its completion has also been extended by two years.

Work started over Kishenganga river in Bandipore district of Jammu and Kashmir in October 2009 and was to be completed in five years.

Due to objections raised by Pakistan, which is protesting the diversion of river waters for the hydroelectric project citing provisions of the Indus Water Treaty, the project will get completed only by 2016, say power department officials.

Pakistan had raised objections over the 450 MW Baglihar power project in Ramban district of Kashmir. The project was to be completed in 2004, but it could be done only by 2008.

"Pakistan should have no objection as the project construction follows all norms of the Indus Water Treaty," a senior officer of the state government told IANS.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.