KEPCO cannot keep resorting to bonds to pay fossil-linked debt

By Christina Ng

State-owned electricity provider Korea Electric Power Corporation (KEPCO) may be running out of tricks to resolve its debt problems.

Last week, the National Assembly of South Korea declined a request to ease KEPCO’s bond issuance limit to help the company repay debt. The reasoning for the rejection: KEPCO must first rectify its management issues.

The thumbs-down signals that lawmakers are tired of enabling KEPCO’s debt addiction and mismanagement without a clear strategic direction out of its fossil-reliant future.

Alongside operating cash flow difficulties and a record US$23 billion in losses for 2022, the debt ceiling rejection does not bode well for the utility’s bond investors.

South Korea’s credit crunch fears 

On 8 December 2022, parliament voted on a bill to increase KEPCO’s corporate bond issuance limit. The bond market is the company’s main financing avenue, and bonds make up the bulk of its borrowings.

KEPCO’s debt ceiling is capped at twice its equity capital and reserves. The bill called for the ceiling to be increased to five times equity and reserves, or six times in emergency cases, which KEPCO said would significantly raise the amount of bonds the company could issue to service existing debt, improve its operating cash flow and provide a stable electricity supply for the country.

The bill was rejected. 

Members of parliament believed that addressing KEPCO’s financial challenges by issuing more debt would not resolve mismanagement, the root cause of the utility’s problems.

One member commented: “If money from the capital market is absorbed to increase the debt of AAA companies without solving the fundamental cause, private companies will run out of money and a crisis situation will happen to the Korean economy.”

KEPCO’s fossil-led disaster

The Institute for Energy Economics and Financial Analysis (IEEFA) considers the rejection a wise decision. 

Just two weeks ago, IEEFA presented the issues that led to KEPCO’s financial difficulties to members of the National Assembly, including its carbon neutrality special committee.

Our analysis found that KEPCO had been slow to switch to renewables compared to its global peers. Instead, the company had been doubling down on fossil fuels even while the evidence was clear that high and volatile coal and LNG prices largely determined its operating margins. As KEPCO had done nothing to correct its investment decisions, the inaction led to recurring operational losses for most of the last decade and a steady increase in debt despite the company already being overleveraged.

Compared to other major utility companies in Asia, such as Hong Kong’s CLP Power Hong Kong Limited, China’s Huaneng Power International, India’s NTPC Limited and Malaysia’s Tenaga Nasional Berhad, KEPCO has also fallen short on every metric. 

Additionally, KEPCO’s decarbonization plan involves expensive fossil-reliant technologies that have not been proven credible. This includes carbon capture and storage and blue hydrogen, which the company is in no position to splurge on, nor is it known to have expertise in, creating additional risks for its investors and the South Korean market.

In May 2022, KEPCO announced that it planned to sell coal and gas-fired power plants outside the country to improve its financial situation and repay debt. IEEFA questioned in its October report who would be willing to buy these soon-to-be stranded assets. KEPCO’s most recent debt ceiling request suggests nobody.

There’s only one way out

KEPCO will not hit its peak bond maturity until 2025 – yet it faces refinancing risk close to US$9 billion within the next 12 months, given the potential default and the lack of clear strategy out of this mess. In any case, the refinancing cost will likely be much higher and would add to the company’s woes.

Further tariff hikes are said to be its means of salvation. However, IEEFA considers meaningful tariff adjustments unlikely, given the high inflation environment and the possibility that any raise would not fix KEPCO’s mismanagement issues. 

Government intervention seems the only credible way out. But it should be accompanied by an immediate, material and enforceable pivot to renewables, a significant cost-cutting exercise that phases out substantial fossil fuels, and a rethink of the composition of management and the board.

Follow the link for more news on

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.