EDF Renewables and KOWEPO reach financial close for 500 MW Oman solar project

The Manah 1 solar project is estimated to supply power to over 50,000 Omani households.

A consortium by EDF Renewables and Korea Western Power Corporation (KOWEPO) has achieved a financial close on Manah 1, a 500-megawatt (MW) solar power plant in the Sultanate of Oman.

After the bid submission in September 2022, the consortium signed a 20-year Power Purchase Agreement (PPA) with Oman Power and Water Procurement Company (PWP) on 23 March 2023.

Under the PPA, EDF and KOWEPO will plan, fund, construct, and manage the plant, which is projected to start commercial operations in Q1 2025. Several major French and Korean energy leaders contributed to the financing of the solar project.

ALSO READ: Renewables lead APAC power project pipeline

Located in the Al Dakhiliyah Governorate, south of Muscat, Manah 1 is the first for EDF Renewables and KOWEPO in the territory. It is one of the consortium’s goals to support the region’s net-zero plans and to contribute to Oman’s Clean Energy Goals of 35% to 39% renewable generation by 2040.

When operational, with over one million bifacial PVs, the solar power project is estimated to supply to over 50,000 Omani households with clean electricity and offset over 700,000 metric tonnes of carbon dioxide per year.

“This first for the consortium large-scale renewable installation in the country is perfectly in line with the EDF Group commitment to triple the renewable energy net capacity in operation worldwide, between 2023 and 2030,” Olivier Bordes, CEO Middle East of EDF Renewables, shared of the consortium’s energy goals.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.