Jindal Power's expansion project gets thumbs up

India's Environment Ministry has given in-principle clearance for Naveen Jindal-led Jindal Power's US$2.9 billion expansion project in Raigad.

 


It paves the way for engineering and construction work to resume at the plant site in Chhattisgarh after a brief hold-up.

The ministry's approval is only for the first two 600-MW units under the expansion project -- which envisages capacity addition of 2,400 MW through the installation of four new 600 -MW powertrains at the Tamnar plant, in Gharghoda tehsil of Raigad district -- as coal linkages have already been granted by the Coal Ministry.

"Environmental clearance shall be applicable for 2x600-MW only. However, at a later stage, when firm coal linkage for the third and fourth unit of 600 MW are also available, the project proponent may request the ministry for inclusion of 2x600-MW, which the ministry may consider appropriately on merit," the ministry said on its website.

The Environment Ministry had withdrawn the preliminary environmental clearance accorded to the Tamnar power project in June, 2010, after certain quarters alleged that Jindal had not followed the Terms of Reference stipulated by the government while carrying out studies to assess the potential impact of the project on the environment.

As a fallout of the decision, Jindal Power was forced to halt all activities at the project site. However, following the in-principle approval accorded to the project by a panel of the Environment Ministry, the Naveen Jindal-led company can restart work on the plant, subject to fulfillment of certain conditions.

Among those stipulated by the ministry for the grant of final environmental clearance, the company has been asked to secure certain permissions from the Coal Ministry, as some of the plant area falls in coal-bearing area.

 

Follow the link for more news on

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.