GREL on track for Vermagiri CCPP commissioning

 

GMR Rajahmundry Energy Limited is on track to meet the commissioning deadline for the 768 MW combined cycled power plant. A GMR Energy-subsidiary, GREL has already wrapped up around 68.8 per cent of the overall project in Vermagiri, with 80 per cent of equipment procured and one-third of the construction done.


 While the structural works for the switchyard and erection of the battery bank and charger have been completed, the erection of cable tray and unit auxiliary transformers is presently underway.


Foundation excavation for gas conditioning system has also commenced at the project site.


Besides, both the generator and gas turbine sets, have reached the site and other equipments like the Heat Recovery Steam Generator modules, switchyard, electrical equipments etc. have also started reaching the venue.

Equipment like boiler pumps, cooling water pumps, condenser tubes, transformer relay protection have also reached the site.
 

Follow the link for more news on

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.