Mundra UMPP Unit-I boiler light-up due this month

CGPL will conclude the boiler light-up for the first unit of the 4,000 MW Mundra UMPP by end of this month. It was originally scheduled on February 2011.


Coastal Gujarat Power Limited, a Tata Power subsidiary,  wanted to achieve ahead-of-schedule commissioning of the 4,000 MW Mundra UMPP.


Thereafter, CGPL will achieve steam blow-off for the unit within the next month, two months before the schedule of April 2011.


Furthermore, erection of boilers for all the five units are presently underway at the project site, with around 98.5% erection at Unit-I complete.


The developer has also completed the erection of main frame structures for Units IV and V.


Unit-I of the UMPP is slated to achieve commercial operation declaration (COD) in June this year, followed by the Unit-II in December, against the schedule of September 2011 and March 2012, respectively.


Likewise, the third, fourth and fifth units will be commissioned in February, June and September 2012, as compared to their corresponding schedule of July, November 2012 and March 2013.

 

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.