, China

China failed to boost nuke installation capacity to 40GW in 2015

It is behind by 15GW from its target.

China has fallen behind its 12th FYP target to raise its nuclear installation capacity to 40GW by the end of 2015, with only 24.14GW installed as of 15 September. This is mainly attributed to the temporary suspension of inland nuclear project approvals. Following the Fukushima accident in 2011, only two projects in coastal area have been approved: Tianwan phase II nuclear project, approved in December 2012 and Liaoning Hongyanhe No.5&6 units, approved in February 2015.

Evan Li, analyst at HBSC, said that although China is set to fall short of its target in 12th FYP, its target for 2020 has remained unchanged at 58GW, as laid out in the latest Energy Development Strategy (2014-2020). "We expect China to speed up the pace of nuclear project construction and approval if it keeps the 58GW target for 2020 in the 13th FYP," he added.

Fundamentals of nuclear power have remained positive, as China continues to nurture this industry as its low-cost solution to de-carbonise power supply. "We continue to favour companies with high exposure to the nuclear space as China plans to grow nuclear capacity to 58GW by 2020, implying a 19.4% CAGR, supported by a clear policy direction and investment pipelines (the construction cycle is seven years)," Li said.

Following China’s recent pledge on climate change to the United Nations, there could be a further policy-driven expansion of nuclear capacity to reduce emissions.

A carbon tax programme to discourage the use of fossil-fuel-based power generation could also be positive for nuclear plays but negative to conventional thermal power equipment makers  

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.