, India

Reliance Power to commission Sasan project

Reliance Power will commission the first unit of its 3,960 MW- Sasan Ultra Mega Power Project in January 2013.
schedule.

 

As per the power purchase agreement, the first unit was to be ready by May 2013. According to the company, the six units of 660 MW each would be commissioned by June 2014.

“Sasan, with its landmark tariff of Rs 1.19 per Kwh, will benefit power consumers in seven states due to its early commissioning,” said Reliance Power CEO J P Chalasani.

Sasan project is estimated to cost around USD 4.3 billion, with financing by an equity contribution of USD 1.2 billion and term loans to the tune of USD 3.1 billion.

Based on super-critical technology, Sasan UMPP is a pit head coal-fired power plant and the company has entered into a 25-year PPA with off takers of power for the entire 3,9602 MW capacity.

Power generated from Sasan would be supplied to seven states — Madhya Pradesh, Punjab, Uttar Pradesh, Delhi, Haryana, Rajasthan and Uttarakhand.

Follow the link for more news on

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.