Private nuclear power players suffer bottlenecks in Indian sector: analysis

Participation is heavily challenged by a "weak management" of contracts.

India has an ambitious nuclear energy programme but its legislative-regulatory mechanism does not quite match up to it. Niharika Tagotra from the Institute for Peace and Conflict Studies, said in an analysis that with a present installed capacity of 5780 mega watts (MW), contributing about 3 per cent to the total energy production, nuclear power in India is produced primarily by its Pressurised Heavy Water Reactors (PHWRs) that operate at a Plant Load Factor (PLF) of 50 to 60 per cent given the shortage of uranium fuel supply.

India aims to produce anywhere between 45,010 MW (optimistic scenario) to 78,060 MW (highly optimistic scenario) of nuclear energy by the year 2047 as per the Indian Energy Security Scenario (IESS).

In sum, by 2047, India will need to develop and commission around 55 new nuclear power plants in order to be able to substantially increase the share of the percentage of nuclear power generated. The energy scenario however faces innumerable bottlenecks including a laggard energy bureaucracy as well as a series of legislations pieced together in an incoherent manner.

Here's more from the analysis:

In order to increase the pool of finance for its nuclear power projects and lessen the duration required for construction of nuclear power plants, the government will also need to look at increasing the participation of private players and regularise the flow of investments to the cash- crunched nuclear energy sector. Currently, India sees a very low participation by the private sector in its nuclear energy industry. The participation from the private industries has been limited to the supply of components, equipment, and works contracts, partaking in the sector only as junior equity partners. Companies like BHEL, L&T and WIL have been awarded contracts for the manufacture of steam generators and reactor equipment but their participation is plagued with policy delays and other regulatory and bureaucratic issues.

The process of private participation is also hampered by a weak management of contracts by the Nuclear Power Corporation of India Limited (NPCIL). The company uses the L1 method for awarding of contracts. Under the L1 or the ‘lowest bidder’ tender system, the contract is awarded to the bidder who provides a product that meets all the mandatory requirements specified under the Services Qualitative Requirement (SQR) at the least net cost. This, however, comes with its own set of challenges, whereby the tender system fails to take into account the ‘cost-plus’ phenomenon. Bids that are too low to be implemented affect the quality of the products delivered, and lead to contract termination or delays due to litigation.

View the full analysis here.

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.