Transmission woes cause Metro Manila - Rizal blackouts

Eastern Metro Manila and Rizal province experienced rotating blackouts as Meralco implemented manual load dropping due to the shutdown of a transformer bank.

The blackouts were expected to compensate for the shutdown of the Dolores substation of the National Grid Corp. of the Philippines. But Meralco's target of restoring power will be delayed for another three days after its substations tripped due to critical loading and in its attempt to shift load. This caused the eleven cities and towns in eastern Metro Manila and Rizal province subjected to rotating blackouts.

The three substations that tripped were Mandaluyong, Hillcrest and SM-Shangri-La. Meralco said the development “will result in longer duration of power outages in affected areas.”

The series of power outages began late Wednesday night, 7 October, in several parts of Metro Manila and Rizal after power was cut off to 13 Meralco substations including those situated in St. Anthony, Manggahan, Parang, Masinag, Marikina, Santolan, Cainta, Shangri-la, Mandaluyong, Hillcrest, Dolores, Cubao bank no. 2 and New Teresa. This resulted to outages in various portions of Mandaluyong, Pasig, Marikina, Taguig; parts of Quezon City including Cubao. Outages were also experienced in Cainta, Angono, Taytay, Binangonan, Antipolo, San Mateo and Montalban.

As of 11:40 p.m., Wednesday evening, power has already been restored to most of the affected areas after Meralco opted to shift load or transfer sourced power to operational substations. Only Dolores 44XM and portions of Dolores 47 XM were not restored.

At 6:39 a.m. Thursday, 8 October, Meralco resorted to MLD affecting circuits served by Cubao and Marikina substations in order to ease the critical loading of Araneta-Kamuning 115 kV line.

NGCP said that at 8:48 p.m. Wednesday, one of four 300-megavolt ampere transformers caught fire, triggering the tripping of the other transformers and five 115-kilovolt lines of Meralco. The fire was contained at around 10:30 p.m.

Supt. Manuel Pion, Taytay's chief of police, said security guards of the NGCP claimed they heard a loud explosion before they saw the transformer on fire. Pion said the facility is fenced and well guarded, and that the possibility of sabotage was remote.

Follow the link for more news on

PT Jawa Satu Power mulai mengoperasikan pembangkit listrik tenaga LNG sebesar 1.760 MW di Indonesia

Pembangkit ini dapat memproduksi listrik untuk 4,3 juta rumah tangga.

Barito Wind Energy mengakuisisi mayoritas saham di PT UPC Sidrap Bayu Energi

Perusahaan ini akan memegang saham sebesar 99,99% di perusahaan tersebut.

Grup NEFIN bekerja ekstra keras dalam mengejar proyek-proyeknya

CEO Glenn Lim menjelaskan bagaimana keterlambatan berubah menjadi hal baik karena perusahaan bertujuan mencapai kapasitas 667 MW pada 2026.

Summit Power International menyediakan dukungan LNG yang vital untuk Bangladesh

Tanpa pasokan listrik cross-border, LNG diperlukan oleh negara yang menghadapi kendala geografis untuk menerapkan sumber energi terbarukan.

JERA, mitra unit PT PLN untuk pengembangan rantai nilai LNG

MOU juga mencakup studi kemungkinan konversi ke hidrogen, rantai nilai amonia.

VOX POP: Bagaimana teknologi vehicle-to-grid dapat meningkatkan transisi energi?

Teknologi vehicle-to-grid (V2G) dipandang sebagai inovasi revolusioner menuju ketahanan jaringan listrik dan peningkatan transisi energi yang kokoh.

IDCTA: Partisipasi global dapat meningkatkan penjualan kredit karbon Indonesia

Pasar karbon Indonesia yang baru dibuka memiliki sebanyak 71,95% kredit karbon yang belum terjual pada akhir 2023.

Bagaimana Asia Tenggara dapat mencapai potensi biogasnya

Kawasan ini hanya memiliki sekitar satu gigawatt kapasitas dengan Thailand, Indonesia, dan Malaysia memimpin dalam hal produksi.