, India

Techno-commercial bids for Kutehr HEP to be in by May end

JSW Energy Limited has set a deadline of May-end for submission of technical and commercial bids for its 240 MW Kutehr HEP.

 

The Central Electricity Authority accorded techno economic concurrence for the project during October last year. Environment clearance has been recommended by the expert appraisal committee of the Ministry of Environment and Forests.

The approved completion cost of the project stands at Rs 1,798.13 core, in the form of equity contribution of Rs 449.53 crore and domestic commercial borrowings worth Rs 1,348.60 crore. Out of the total, the hard cost, IDC and FC components are estimated to be Rs 1,437.45 crore, 353.94 crore and 6.74 crore, respectively. Till March 31, 2011, about Rs 119 crore has been expended on the project.

The project is a run-of -the-river hyropower project on Ravi river in the Chamba district of Himachal Pradesh. It involves construction of a 14.6-km long concrete lined, circular shaped HRT with a diameter of 6.2 m and a circular 275
 

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!