NTPC blames agencies for sluggish work at Bongaigaon TPP

NTPC blames BHEL and SPML for delays in its 750 MW Bongaigaon thermal power plant.

 

It said that Bharat Heavy Electricals Limited was delayed in supplying the generator stator while Subhash Projects and Marketing Limited guilty tardy pace of works.

In its defense, BHEL has explained that it is still awaiting the pending railway clearance for 1 out of 5 zones and has promised to immediately dispatch the stator to the project  once the requisite approval has been granted by the Ministry of Railways.

Alongside this, BHEL's inability to finalize the turbine generator erection agency has delayed the commencement of the TG erection process, thereby forcing NTPC to revise the schedule for completion of oil flushing and TG rolling and synchronization to the second half of the year 2013.

On the other hand, the excruciatingly slow pace of works by the civil contractor SPML has pushed forward the date of completion of critical milestones such as boiler light up and TG box up to August and October 2012, respectively.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!